The IRAM program committee convened in Grenoble on October 22 and 23 to evaluate the proposals submitted for the winter 2013/2014 scheduling period. The discussions were organized in 2 panels which were chaired by Christian Henkel (MPIfR, Bonn) and Valentin Bujarrabal (OAN, Alcala de Henares). The principal investigators of each proposal will be informed by letter which will include comments issued by the committee if there are any.  As usual, the proposals were classified A (accepted), B (backup), and C (rejected).

Plateau de Bure Interferometer Proposals

A total of 125 proposals were received for the interferometer, including one proposal that was submitted in the "Large Program" category. Proposals rated A will be scheduled in priority. Further time, if it becomes available, will go to the B programs, taking into account scientific merit, crowding in certain right ascension ranges and general aspects of balance.

For proposals rated A or B which do not have an IRAM internal collaborator, please consult the list of local contacts. The accepted proposals are listed here.
 
 

A: Accepted, B: Backup, C: Rejected

 Project  Rate  Project  Rate  Project  Rate  Project  Rate  Project  Rate  Project  Rate  Project  Rate  Project  Rate 
X056BX057CX058AX059BX05AAX05BCX05CCX05DC
X05ECX05FBX060AX061CX062CX063CX064CX065B
X066BX067BX068CX069BX06ABX06BAX06CBX06DA
X06EBX06FBX070BX071BX072BX073AX074BX075C
X076BX077CX078BX079BX07ACX07BBX07C---X07DC
X07ECX07FAX080CX081BX082CX083CX084CX085C
X086CX087AX088CX089CX08ACX08BBX08CCX08DC
X08ECX08FAX090CX091BX092CX093BX094BX095B
X096CX097CX098CX099CX09ACX09BCX09CAX09DC
X09ECX09FCX0A0CX0A1BX0A2BX0A3CX0A4BX0A5C
X0A6CX0A7---X0A8CX0A9BX0AACX0ABCX0ACCX0ADB
X0AEBX0AFA¥X0B0CX0B1BX0B2AX0B3AX0B4CX0B5C
X0B6CX0B7CX0B8CX0B9---X0BAAX0BBCX0BCAX0BDB
X0BECX0BFCX0C0CX0C1CX0C2BX0C3CX0C4CX0C5C
X0C6BX0C7CX0C8AX0C9CX0CABX0CBCX0CCAX0CDB
X0CEBX0CFBX0D0CX0D1CX0D2A
:  some parts of the program - others rated B or C
:  with time restrictions
--- : not rated
¥:   time filler

30m telescope

We received 140 proposals for the 30m telescope, including those requesting short-spaging observations. No Large Program were submitted this semester. Together, the new proposals amount to a total of 4050 hours of telescope time, of which about 45% goes to galactic proposals.

The highest rating "A" was given to 44 proposals, and 48 proposals were rated "B", i.e. were given backup status. The remaining proposals, although scientifically valuable in most cases, were rated "C". The individual ratings are listed in the table below. All A-rated proposals will be scheduled on the telescope, although some with less time than requested. We expect that about half of the B-rated programs will actually be scheduled. The selection will take into account scientific merit, crowding in certain right ascension ranges, and general aspects of balance. Proposals rated "C" will not get telescope time.

The accepted proposals are listed here. The short spacing proposals will be scheduled on the 30m if they get observed at Bure.

IRAM 30m Telescope Proposal Ratings:   winter 2013/14

(short spacing proposals not included)

A

B

C

  114-13   118-13   121-13   115-13   117-13   120-13   125-13   116-13   119-13   123-13
  122-13   128-13   129-13   126-13   138-13   140-13   144-13   124-13   127-13   131-13
  130-13   132-13    133-13   147-13     151-13     152-13   160-13   135-13   139-13   141-13
  134-13   136-13   137-13   163-13   164-13     165-13   166-13   148-13   153-13   154-13
  142-13   143-13   145-13   167-13   170-13   172-13   173-13   155-13   158-13   159-13
  146-13   149-13   150-13    174-13   177-13   182-13   186-13   168-13   169-13   178-13
  156-13   157-13   161-13   189-13   190-13   192-13   193-13   180-13   181-13   187-13
  162-13   171-13   175-13   195-13   196-13   197-13   205-13   188-13   199-13   201-13
  176-13   183-13   184-13   208-13   210-13   211-13   217-13   202-13   203-13   204-13
  185-13   191-13   194-13   221-13   222-13     224-13   226-13   206-13   207-13   209-13
  198-13   200-13    214-13   227-13   230-13   231-13   232-13   212-13   213-13   218-13
  215-13   216-13   220-13   235-13   236-13   242-13   244-13     219-13   225-13   228-13
  223-13   233-13   234-13           229-13   238-13   241-13
  237-13   239-13   240-13           243-13    
  245-13   246-13                

¹ time reduced
² part of time rated B IRAM 30m Proposal Processor